TIRANA, January 14 /ATA/ The Chairperson of the Parliamentary group of the Socialist Party Taulant Balla, accompanied by MP Luan Duzha, saw closely the works that are being carried out for the reconstruction of the electricity distribution network in Cërrik.
According to Balla, thanks to the investment that is being made for the system of low voltage for the area of Shtermen, Gostima and Floq will benefit 2300 subscribers.
“This is a very important investment that the local residents of these areas have been looking for long ago. With the investment of 1.2 million euros, 23 electric cabins have been installed, 800 new poles and about 60 km of new cable has been laid. In the region of Elbasan, during this year are invested about 5 million euros in the entire electricity distribution network “, stated Balla. /m.m//a.a/r.e/p.s./