TIRANA, June 21 /ATA/ The new administrator of Albanian Power Corporation (KESH), Ergys Verdho, visited the hydropower plant of Fierza to see first-hand the investments in progress, the needs for improving the working conditions and the new projects that will increase the performance of HPPs.
During this visit, Verdho had a conversation with the staff about a number of issues to ensure smooth running of processes and increase of productivity.
Also, the administrator of KESH inspected the investments that are underway in Fierza HPP such as the progress of electro-mechanical rehabilitation works in the discharge tunnels no. 3 and no. 4, the progress of the rehabilitation works on the overhaul gates in the lower part of the hydropower plant, an investment through KESH funds, etc.
KESH sh.a will continue to invest in increasing the technical readiness for operation and technical longevity for the use of works. /j.p/r.e/sm/