Construction works on Arbër Highway running at high rates

TIRANA, July 18/ATA/-  The Albania’s Prime Minister Edi Rama shared Thursday in the social media a video showing the construction site of the Arbër Highway running at high rates.

T5 tunnel has a length of 500 meters and is completely built, except for the asphalt layer.

The Vasha Bridge is due to end during summer time as considered as one of the highest bridges in the region, 150 meters from the level where it started.

According to the contract the deadline for construction of the road is November 2021, but the road will be built by spring 2021.

In addition to its panoramic aspect, it will be rather attractive for the numerous visitors who can have a taste of the beauties of the surrounding area while travelling along the road.

There are 7 tunnels along the road with a total length of 8.5 km, of which up to now are fully opened 5 tunnels and the work is continuing with opening of Murriz tunnel. So far, there is opened up to 2.8 km of tunnel.

The Vasha bridge connects the two tunnels T5 and T6 to the two mountain slopes.
The entire part of Arbër Highway that is to be built is 54 km at length, in which the concessionaire has realized about 40% of the works.//a.i